CAMBRIDGE - CIVIL & PRIVATE SITEWORKS
Client: Naylor Love
Status: Complete
PROJECT OVERVIEW
This project, initiated by Naylor Love, involved the removal of an existing pool and concrete surround, followed by extensive excavation and site preparation for a new community pool.
PROJECT SCOPE
The scope encompassed breaking up and removing the existing pool and concrete surround, excavating a new 17x9m concrete slab area to a depth of 300mm, and removing topsoil. The team supplied and installed 200mm of crushed concrete from an adjacent site, topped with 100mm of compacted pit sand.
COMMUNITY BENEFITS
This completion of this project ensured that the Cambridge community will have access to modern pool infrastructure for many years to come.